Southeastern University Operations Management & Machine Utilization Essay Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that th

Southeastern University Operations Management & Machine Utilization Essay Question 1:

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine HoursDue Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5)
What is the makespan?
How much machine idle time is there?
How much idle time (waiting time) is there for each job?
When is each job delivered?
Which department is the bottleneck?
Calculate the machine utilization?

Question 2:

A public accounting firm requires the following activities

for an audit:

Activity

Immediate Predecessor

Activity time

A

3

B

A

2

C

5

D

B, C

2

E

A

4

F

B, C

6

G

E, D

5

Draw a network for this project?
Make a forward pass and a backward pass to determine ES, LS, EF, and LF?
What are the critical path?

** A clearer version of the table with attachments Assignment Question(s):
Question 1:
Sequence the jobs shown below by using a Gantt chart. Assume that the
move time between machines is one hour. Sequence the jobs in priority
order 1, 2, 3, 4.
Job Work Center/Machine Hours
Due Date (days)
1
A/3, B/2, C/2
3
2
C/2, A/4
2
3
B/6, A/1, C/3
4
4
C/4, A/1, B/2
3
a) Using finite capacity scheduling, draw a Gantt chart for the schedule
b) What is the makespan?
c) How much machine idle time is there?
d) How much idle time (waiting time) is there for each job?
e) When is each job delivered?
f) Which department is the bottleneck?
g) Calculate the machine utilization?
Question 2:
A public accounting firm requires the following activities
for an audit:
Activity
A
B
C
D
E
F
G
Immediate Predecessor
A
B, C
A
B, C
E, D
Activity time
3
2
5
2
4
6
5
a) Draw a network for this project?
b) Make a forward pass and a backward pass to determine ES, LS, EF,
and LF?
c) What are the critical path?

Purchase answer to see full
attachment

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.